Golden Gate Bridge Overnight Lane Closures Begin as Seismic Retrofit Advances

Drivers who rely on the Golden Gate Bridge after dark should brace for a week of overnight lane closures as construction crews ramp up work tied to the bridge's decades-long seismic retrofit.
The closures began Monday, Oct. 5, with two southbound lanes and one northbound lane shutting down at 9 p.m. All lanes are scheduled to reopen by 5 a.m. each day, but the same three lanes are expected to remain out of service overnight through Friday morning, Oct. 9. During those hours, the bridge will operate with three open lanes, so drivers should expect slower crossings and possible backups.
Crews will install about 230,000 square feet of decking, a precursor to the next phase of the $1.8 billion retrofit. That effort, in the works for decades, is intended to make one of California's most recognizable landmarks more resilient in a major earthquake.
The upcoming work includes strengthening and reinforcing the main span between the two towers, along with the two side spans. Crews also plan to add floor beams, replace expansion joints, install new struts, add latticework to the roadway and fit giant shock absorbers designed to reduce vibration from seismic tremors.
Officials want the bridge to withstand an 8.3-magnitude earthquake on the Richter scale, a scenario considered comparable in strength to the 1906 San Francisco earthquake that devastated the city.
For late-night travelers trying to avoid the closures on the drive back into the North Bay, alternatives are limited. San Francisco Bay Ferry and Golden Gate Ferry provide service from Vallejo, Larkspur, Sausalito and Tiburon to San Francisco, but each route stops running a couple of hours before crews begin closing lanes.
It remains unclear when long-term construction will officially begin on the bridge, but the first half of the project is expected to last up to six years.
The reinforcement work marks the final phase of the Seismic Retrofit project, which has been in development for nearly 30 years. The Golden Gate Bridge is also among the last California bridges to receive such strengthening, a requirement that followed the 1989 Loma Prieta earthquake. That magnitude 6.9 quake struck the San Francisco Bay Area, killing 63 people and injuring more than 3,700.
The Board of Directors of the Golden Gate Bridge Highway and Transportation District awarded the project's first contract in 1997 and established a construction administration team of district staff and consultants to determine an optimal plan.
In 2001, the district began the second phase, retrofitting structures in the bridge's southern portion, including the south approach viaduct, Fort Point arch, south pylons and south anchorage housing. That work was completed in 2008 without closing the bridge to traffic.
In April 2008, crews started a similar retrofit on the North Anchorage Housing, which was completed in 2014.
Nearly a decade would pass before the district began planning the final portion of the retrofit: reinforcing both towers and the south tower pier.
The Golden Gate Bridge is one of California's most recognizable landmarks. Construction began in 1933, and the bridge opened in May 1937 after four years of work. Its 4,200-foot main span was the longest suspension bridge in the world at the time and helped transform travel between San Francisco and Marin County.
Nearly 90 years later, the bridge remains a global symbol of San Francisco and one of the nation's most visited attractions. A 2023 analysis by travel platform Explore Worldwide ranked it the sixth most popular landmark in the United States.
Today, roughly 89,000 vehicles cross the bridge each day, making it one of the Bay Area's busiest transportation corridors. Drivers pay a toll only when traveling southbound into San Francisco; FasTrak users are currently charged $10.25 per crossing.
This article originally appeared on USA TODAY: Golden Gate Bridge closes lanes to prepare for retrofit construction