Trump’s Triumphal Arch Could Bring Years of Traffic Detours Near Arlington Memorial Bridge

WASHINGTON — President Donald Trump’s proposed 250-foot Triumphal Arch near Arlington National Cemetery would sit at Memorial Circle, just across the Arlington Memorial Bridge from the Lincoln Memorial. Before any stonework rises, though, drivers could face two to three years of shifting traffic patterns, temporary closures and rerouted turns, according to construction plans filed with the National Capital Planning Commission.
The National Park Service report outlining the project’s construction effects says several movements around Memorial Circle would be restricted while work is underway.
- Washington Boulevard: Northbound drivers would not be able to enter Memorial Circle and would be required to turn right onto Arlington Memorial Bridge.
- Memorial Avenue: Eastbound drivers would lose the ability to turn north onto Arlington Boulevard and would be directed onto Arlington Memorial Bridge instead.
- Arlington Memorial Bridge: Westbound traffic approaching the circle would be narrowed to two lanes.
For most of the construction period, the southern side of Memorial Circle would be closed, with eastbound traffic from Memorial Avenue routed around the northern side. The report also calls for temporarily moving the south-side sidewalk to the north side.
The work is expected to generate significant truck traffic. The Park Service estimates that 20 to 30 trucks would make roughly 80 to 100 loads a day, mainly using I-395 and Route 27 to reach the construction staging area. Trucks would be staged and loaded inside the site to reduce congestion on nearby roads.
Additional closures and detours are expected as crews set up traffic controls, install utilities and finish work near the end of the project, the report says. It does not specify when individual closures and detours would occur.
The effects would not be confined to Memorial Circle. In June, Arlington officials wrote to the National Capital Planning Commission that the temporary closures and detours would have regional traffic consequences beyond the immediate work zone. They called for a broader detour and circulation plan to show how regional traffic would be redirected around and outside the area, and how those changes would affect parallel roadways.
The project is expected to take about two to three years, according to materials submitted by the National Park Service. The temporary restrictions would apply only during construction and are separate from proposed traffic changes that would remain after the arch is completed.
For drivers who use the corridor between Washington and Arlington, the plans suggest years of adjustments around one of the region’s most visible memorial landscapes — with effects likely to extend beyond the circle itself as trucks, detours and lane shifts ripple onto nearby roads.